Quantcast

Sarasota Review

Tuesday, October 28, 2025

CITY OF VENICE: Fire Station 1/City Hall Expansion project UPDATE 7/24

Construction

City of Venice issued the following announcement on July 24

The contractor for the Venice Fire Station 1/City Hall Expansion project has begun work along the north side of City Hall, where the stormwater retention ponds are being reshaped and expanded. These ponds will be providing the water treatment and pollutant removal for the new Fire Station and the City Hall Expansion. Next week, the contractor will continue the pond grading work on the north side of City Hall and will begin selective demolition of the existing colonnade structure that is located adjacent to the City Manager’s and Cashier’s offices. They are also planning to start hauling fill next week to begin building the foundation pad for the new structures.

Original source can be found here.

Source: City of Venice

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS